
Replacing the measuring system
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Deutschland
41
English
7 Replacing the measuring system
The following points must be noted when replacing the measuring system:
● The new measuring system must have the same item number as the system
being replaced. Any deviations from this must be cleared with Pilz.
● You must ensure that the count direction set via hardware switches on the new
measuring system matches the previous count direction.
● The new measuring system must be installed in accordance with the
specifications and requirements stated in the chapter entitled “Assembly”.
● The new measuring system must be connected in accordance with the
specifications stated in the chapter entitled “Connection/Shield connection”.
● When recommissioning the replaced measuring system, a protected test run must
be carried out to ensure the system functions correctly.
Comentários a estes Manuais